Thu Sep 02, 2010 10:38 pm
 
  BC Program Support Log

Superior Issue ,
Change, and Risks
Management
Download

Prices

Screen Shots
 
 
 
 
 
 

Hosting your BC Applications
with us works because you can
concentrate on your business

 

It's Simple!

We Work, You Produce!

Awards

Not that we're counting but;)
Bill Catchem Software has earned over 200 5 Star and Editors choice awards.

Service is where
we really shine!

 

Risks

Risk Impact Analysis

Risks
A structured approach to managing and monitoring risk.

Definition: Risk is a term that refers to events, which, if they occur, may have a negative impact on a project and bring unwanted consequences. It is not unusual to have some confusion between a risk, an issue, and a change request.  They can be differentiated as follows:

Item

Description

Risk

Something negative that may happen in the future.

Issue

Something that is occurring now and has to be resolved. Unresolved issues may put the project at risk.

Change Request

A request that seeks permission for a specific course of action to be taken (perhaps to resolve an issue or a risk).

Risks are possible events. Events that are actually happening are issues. A risk always has the possibility of becoming an issue.

There is an interrelationship between Issues, Risks and Change Requests as the results of one may trigger the other as per the following diagram:

A risk can be viewed from two dimensions:

  • Impact – Scope /Cost/Quality

  • Probability of Occurrence – The greater the likelihood of the events, the greater the risk.

The Ernst & Young Navigator Systems Series defines a risk management strategy as a means of minimizing the probability and impact of a known risk factor on the project. There are four ways of managing risk:

  • Acceptance – live with the risk by accepting the consequences and develop a contingency plan to execute should the risk event occur.

  • Mitigation – take action to reduce the impact and/or probability of the risk.

  • Avoidance – change the circumstances that are creating the risk, usually by eliminating the cause.

  • Transfer – forward a risk to the appropriate body, outside the Project.

To Top

Purpose of Risk Management

All projects have risks. A risk is not negative in itself; instead, a risk can become negative if it is not planned for. Risk management helps you:

  • Anticipating and identifying areas of project risk.

  • Minimizing the impact of identified risks.

  • Reducing the likelihood of identified risks.

  • Monitoring risk areas for early detection and action.

Goals of Risk Management

A series of related goals and accomplishments are identified as:

  • Complying with the Risk Management Policy.

  • Using a risk management as an effective communication tool, which encourages the communication of risk activities for current and emerging risks.

  • Allowing for risk preparedness to be conducted systematically.

  • Encouraging a proactive approach in reducing the impact and/or probability of risk by instituting a cycle of continuous risk management planning.

  • Defining a process to manage risk.

  • Defining a standard approach for impact analysis on risks.
     

To Top

The Risk Management Process


  • Identify the Risk

    Risk identification is the process of identifying all possible future events that may affect the project’s objectives.

    The following questions can help determine if the item is a Risk:
    • Is it a possible event?
    • Will it have a negative impact on the project?

Answering, “yes” to these questions identifies a risk.


  • Open the Risk Incident

    A Risk incident can be initiated by anybody on the project and logged into Program Support Log.

    A Status of ‘new’ is automatically assigned. All ‘new’ Risk incidents are reviewed at the Project Huddle

    The Business or Project Office has the responsibility to update and track all risks from the Program Support Log.

    The Business or Project Office also has the responsibility to review all newly identified risks to determine if a similar risk is already in progress or completed. A scan is done of the existing risks to determine if there is similar one already logged. If a similar risk is already in progress, then it may be appropriate to merge the risks and the status of the new risk is changed to “Merged”.  If there is not a similar risk in progress, then an impact and probability analysis must be conducted on the identified risk.


  • Analyze the Change Request

    Risk Analysis is the process of examining the identified risk and determining and documenting the impact to the project. Analyzing a risk includes an assessment of its impact and probability to generate a risk Impact level (Ranking) and a recommended course of action. A risk can be withdrawn at any point by the originator prior to the completion of the analysis.

    The Business or Project Office will include any newly received risks as an agenda item for the Project Huddle Meeting. The Project Huddle is responsible for vetting the newly identified risk and assigning an individual to conduct a risk analysis. The analysis should be assigned to an individual with the relevant expertise. A target end date for the analysis will also be decided. The Business or Project Office is responsible to update the Program Support Log with the name of the person assigned to perform the analysis and the target end date. The status of the risk is changed to ‘Under Investigation’.

    Impact Analysis

    The impact analysis answers the question, what would happen if the risk occurred?

    Impact Analysis is done against three factors: Scope, Cost, Quality, plus the Probability of Occurrence.

    The probability of the risk occurring is not only dependent on the statistical concept of chance; it must also take into account the level of difficulty to address the risk.

    The probability of the risk is assessed against two factors:
    • Likelihood - how likely is it that the risk will occur?
    • Resolution - how difficult would it be to resolve the risk?

Establish the Risk Level
The risk level establishes the priority of the risk. The Expected Value of the risk is the numeric Impact Score (highest impact score) multiplied by the numeric Probability Score (lowest probability score).

Probability Score X Impact Score = Expected Value
A rating level of Urgent, High, Medium or Low is based on the Expected value.

Once the Risk Level is entered into the Program Support Log, the status of the risk is be changed to "Completed Analysis".  Any notes, assumptions, and sources of information that were used to conduct the analysis should be entered into the Analysis Description Text field of the Program Support Log. Other Areas and Stakeholders impacted by the risk must be identified. A recommended course of action to resolve the risk must be provided. It will be up to Approval Authority to approve a recommended course of action

The Risk response Plan encompasses a wide variety of activities.  For instance, change requests may be required, and the corresponding activities may have to be added to the appropriate detailed project plan.
 


  • Resolve the Risk / Selecting a Course Of Action.


    With the analysis completed, the appropriate Approval Authority can be selected. There are two important considerations for selecting the Approval Authority.

    First, which organization will be primarily responsible for implementing the recommendation?

    Second, the higher the ranking of a risk level (Urgent, High, Medium or Low), the higher the level of Approval Authority required.  As a guideline, consider the following:

Urgent – Directory (or Project Sponsor or Steering Committee)

High – Director

Medium – Manager, Director

Low – Project or Team Leader, Manager, Director

At the Project Huddle Meeting, all risks that have completed analysis will be reviewed and an Approval Authority will be determined. The Approval Authority will be notified that the risk has been analyzed and is ready for review. The detail of impact analysis and recommended course of action must be provided to the Approval Authority. The Approval Authority will decide upon the course of action.

The possible courses of action are:

Action

Description

Accept

Live with the risk and develop a contingency plan to execute should the risk event occur.

Mitigate

Take steps to reduce the impact and/or probability of the risk.

Avoid

Change the circumstances that are creating the risk, usually by eliminating the cause.

Transfer

Transfer the risk to the appropriate body, outside the Project

When a risk is accepted, a Contingency Plan should be considered. A Contingency Plan describes activities that are invoked if the risk occurs. The Contingency Plan should be added to the detailed project plan as a deliverable. The Program Support Log is updated to reflect that a Contingency Plan is being developed and the status of the risk is changed to “Monitor”.

The Approval Authority may choose to initiate some activities to try and mitigate (reduce) a risk. The Approval Authority will assign an individual with relevant expertise and authority to mitigate the risk and will also decide the target end date for the task. The resource assigned to mitigate the risk and a target end date will be entered in the Program Support Log and the status of the risk is changed to “In Progress”. The Analysis Description text field of the Program Support Log should be updated by entering any notes, assumptions sources of information and attaching any supporting documents or URL's that were used to mitigate the risk. The activities that are required to mitigate a risk should be added to the detailed project plan as a deliverable.

The Approval Authority should be notified (Except Steering Committee) when risk mitigation actions are completed. Update to the Steering committee should be provided via Steering Committee Reports. The Approval Authority will review the risk and decide if any further activity is required to close the risk. If no further action is required, then the status of the risk is changed to "Completed".

Based on the analysis, the Approval Authority may choose to avoid or transfer a risk. The Approval Authority will update the Program Support Log with the rational for transferring or avoiding the risk and the status of the risk is set to “Completed”.

Only the Approval Authority can close the risk.

NOTE:  Sometimes a risk may require both mitigating and contingency actions.

 

To Top




Track and Control

The Business or Project Office is responsible for monitoring progress made against risks. The timely resolution of risks is an important element of project success. The Project Huddle Meeting is the forum used to discuss the progress.

Control is the process in which risk mitigation and contingency activities are managed. As part of control, if the mitigating or contingency actions are not completed in a timely manner, a risk must be escalated to the next level of accountability.

The following triggers may result in a reassessment of a risk:

• Scope change to the project (through change control or scope creep)

• Frequent changes in people assigned to the risk

• Change in technology associated with the risk

• Lack of or an insufficient action plan for the risk

• New issue that may impact the risk

• New risk that may impact the original risk, resulting in a cascade effect

• Changes to available money and time to handle the risk

• Changes to available expertise to deal with the risk

 

Risk Management Process Summary

  • Identify the Risk
  • Open the Risk
  • Analyze the Risk

  • Select a Course of Action

  • Track and control

To Top

 

Contact Us | Privacy Policy | Site Map